Birth of a Restaurant

The Construction, Weeks 1 & 2
Once the demolition was complete, the initial phase of construction focuses on installation of the backbone of all restaurant services, plumbing and electrical. The trenching provides access to all equipment requiring waste water drains. Since the front end of restaurant featured an open ceiling, it was necessary to run some of the power lines underground supporting the step wall and bar area. Conduit is run in the trench and the electrical wires will be pulled through the conduit to an appropriate exit point above the ground. One exit point will support power to the step wall and the other will support power and other services (cable, phone, stereo speaker wires, etc) the bar.
               
  Click photos below to enlarge
 
The first run of drain services the bar and ties into the main drain line that runs to the city sewer.

Main drain photo 1
   
Main drain

photo 2
   
   
Rear of kitchen
servicing deep sink
and walk in cooler condensate drain.

Photo 1
   
Rear of kitchen

Photo 2
 
   
Bar water supply lines.

Photo 1
   

Bar water supply lines.

Photo 2
 
 
Bar Service Drain Line.
A larger power panel needed to be installed
to support the increased load demand required
by the restaurant.
 
 
Frames for the bar
and step wall

Reconfiguring the
men’s room to meet
city code

 
 
Framing for the rear
wall of the open kitchen

Photo 1
Framing for the rear
wall of the open kitchen

Photo 2
 
 
Electrical runs being routed through the
inner wall. All penetrations to the inner wall will eventually be sealed.
A firewall will be constructed over the
inner wall adding three additional layers of wallboard to meet the fire code requirements for restaurants
 
 
The open kitchen front wall framing.
The outline of the
Pass can be seen
 
 
     